Two firms bid for additional works of Polavaram Irrigation Project
The New Indian Express | May 19, 2021
The technical evaluation of the bids will be done on Wednesday, followed by commercial/financial evaluation on Wednesday before going for reverse tendering, the officials said.
VIJAYAWADA: Two firms have filed bids for the additional head works of Polavaram Irrigation Project (PIP) in the second call given by the water resources government earlier this month.
The technical evaluation of the bids will be done on Wednesday, followed by commercial/financial evaluation on Wednesday before going for reverse tendering, the officials said.
According to information, Megha Engineering and Infrastructures Ltd (MEIL), which is already executing the head works, is one of the two companies that filed the bids for the additional works.
“Two companies have submitted the bids before the deadline on Tuesday and we will evaluate them on Wednesday. The qualified bids will be considered for financial evaluation, followed by reverse auctioning, with qualified bidders, on Friday,” a senior official from the water resources department said. The estimated value of the works is Rs 683 crore.
For the record, the water resources department had invited tenders last month for the additional works, but later decided to re-invite the bids as the bids filed by two companies that participated in the process had issues. Subsequently, a second call was given and time was given till Tuesday to file the bids.
It is learnt that the department wanted to award works to the existing contractor on nomination basis to ensure momentum in the pace of works as change in an agency would again involve logistic management.
However, the department sent the bids for judicial preview and floated the tender after the government decided to go for bidding.
The additional head works include investigation, survey, preparation of designs and construction of RCC diaphragm wall end cut-off for spill channel, vibro stone columns and others.
Reverse tendering
The technical evaluation of the bids will be done on Wednesday, followed by commercial evaluation on Wednesday before going for reverse tendering.